Survey of North American Water/Wastewater DBO Projects
From Public
Works Financing
For this and other full stories subscribe to PWFinaancing by calling
908-654-0397
Copyrighted Material
Do not reproduce without express permission of Public Works Financing: 908-654-0397
| Arvin, Calif.: 35-yr. DBO of 2-mgd wastewater treatment plant. | USFOS | $54m DBOM fees and costs with $5.5m in capital and corporate financing by USFOS. Awarded 7/98. |
| Wilmington, Del.: 20-yr. lease on 90-mgd wastewater treatment plant slated for expansion to 132 mgd | USFOS | $1 m concession fee to city for transaction costs; $1 2m capital investment; $1 64m in fees and costs. Signed 12/97. |
| Honolulu, Haw.: 20-yr. DBO 12-mgd reverse osmosis reclamation facility | USFOS | $140m in fees and costs. Awarded 10/98. |
| Leominster, Mass.: 20-yr. DBO water and wastewater plants | USFOS | Financed with USFOS and has $36m in fees; $4.lm turnkey upgrade of both systems. Signed 11/96. |
| Lynn, Mass.: Turnkey implementation of a combined sewer overflow solution to CSO problem | USFOS (CSO); Aqua Alliance (con-ops) | $60m capital. Selected preferred bidders 12/99. |
| Plymouth, Mass.: 20-yr. DBO 3-mgd wastewater plant | USFOS | $45m in fees and costs. Awarded 6/99. |
| Taunton, Mass.: 20-yr. service contract to upgrade and operate 8.3-mgd wastewater treatment plant | USFOS | $50m in fees and costs. Signed 8/98. |
| Moncton, NB, Canada: 20-yr. BOT of 27-mgd water filtration plant | USFOS (Hardman Group) |
$59.5m capital. Awarded 5/98. |
| Washington Borough, NJ: 15-yr. DBO for 1 .5-mgd wastewater treatment plant | USFOS | $17.9m in fees; $8.2m capital. Awarded 6/98. |
| Franklin, Oh.: 20-yr. BOT 4.5-mgd wastewater treatment plant | USFOS | $6.8m capital investment to purchase and $1.7m in fees. Signed 8/95. |
| Montgomery County Pa.: 20-yr. OM&M/ DBO regional wastewater plant. Expansion to 12.8 mgd | USFOS | $30m in capital with $66m in fees and costs. Awarded 1/99. |
| Cranston, RI: 25-yr. lease/BOT of $24m wastewater facility excluding AWT upgrade of 23-mgd wastewater system. | USFOS/ Metcalf & Eddy/ Poseidon Resources |
$400m in fees and costs with $48.1 m up-front contract payment to city. Awarded 1 2/96. |
| Woonsocket, RI: 20-yr. DBO 16-mgd wastewater treatment plant | USFOS | $22.4m in capital and soft costs plus a $3.9m concessionfee; $75m in costs and fees. Awarded 4/99 |
| Freeport, Tex.: 20-yr. OM&M upgrade of 1 .5-mgd sewerage system and 2.6mgd water plant | USFOS/ Metcalf & Eddy |
$45m in fees and costs. Signed 4/95. |
| Guam. 20-yr DBO 3-mgd water plant and distribution system | Earth Tech | $45m capital. Under construction 1999. |
| Oak Grove, Ky.: 10-yr. OM&M; DB water plant improvements | Earth Tech | $4m in fees; $lm capital. Signed in 1998. |
| Gardiner, Mass: 20-yr. op., repair, replace 3.5-mgd water and 5-mgd ww systems; DBO new 3-mgd water filtration | Earth Tech | $100m in fees and costs. Awarded 11/98. |
| Traverse City, Mich.: DBO water system | Earth Tech | $6.8m capital. Awarded 7/97. |
| Franklin, Oh.: 20-yr. service contract DBO 5-mgd expansion of water plant | Earth Tech | $15m capital. Started 10/97. |
| Bessemer, Ala.: 20-yr. DBO 12-mgd water plant and trunk main | Ogden Water | $63m in fees and costs. Awarded 6/98. |
| Monroe County, FIa.: 20-yr DBO regional wastewater plant, pipes for Key Largo under evaluation. | Ogden Water | $58m capital, $3m/yr. O&M. Low bidder 1/2000, |
| Bakersfield, Calif.: BOO an initially lO-mgd water treatment plant; to reach 60 mgd at build-out | California Water Service Co. |
$20m capital. Signed 3/99. |
| San Diego. Calif.: 20-yr. BOT sludge pelletizer at Miramar Naval Air Station Water Tech. | Wheelabrator | $20m capital. Commercial operation in 1998 |
| Rangeview Metro District, Colo.: 85-yr. DBO wastewater treatment plant | PureCycle Corp. | Cost NA. Signed 1/97. |
| Tampa Bay, FIa.: 30-yr. BOT 35-mgd RO desalination plant | Poseidon Res./ Stone & Webster |
$120m capital. Signed 7/99. |
| Mt. Vernon, Ill.: BOT 5-mgd expansion of a sewage treatment plant under a 20-yr. O&M contract | Environmental Mgmt. Corp./ Paric Corp. |
$6.64m capital. Commercial operation in 1988. |
| Greater Lawrence, Mass.: 20-yr. DBO sludge processing plant | New England Fertilizer Co. |
$49m capital; $17m 1st yr. fee. Awarded 1998. |
| Edison, NJ: 20-yr. upgrade and O&M a 9-5-mgd water system | Elizabethtown Water Co. |
$120m in fees and costs. Signed 8/97. |
| Cactus-Etter-Amarillo, Tex.: DBO wastewater treatment plant. | CET Enviro. Services Water Quality Mgt. |
$30m capital. Awarded 7/98. |
| Kyle, Tex.: 20-yr. lease DBO a l.5-mgd expansion of 4.5-mgd wastewater plant | Aqua Source | Cost NA. Signed early 1999. |
| San Antonio, Tex.: 10-yr. DBO surface water systems | United Water Services | $30m capital. Signed 3/25/98. |
| Seattle, Wash.: 15-yr. DBO w/two 5-yr. renewals for the 120-mgd Tolt River water filtration plant | Camp Dresser & McKee/Azurix/ Dillingham |
$101m capital. Awarded 3/4/97. |
| Beverly Hills, Calif.: DBO water plant and municipal building | Bidding | Cost NA. Finalists selected. |
| Tampa Bay, Fla.: DBO 60-mgd surface water treatment plant | Bidding | $165m capital. USFOS selected preferred bidder 1/2000. |
| Chicago. Ill.: 20-yr. BOT 150-dry tpd biosolids pelletizing plant | Bidding | $360m capital. To be awarded early 2000. |
| Springfield, Mass.: DBO 43-mgd wastewater upgrade under 20-yr. OM&M | Bidding | $15m capital. Preferred bidder to be selected 3/2000. |
| Glens Falls, NY: DBO surface water filter plant, OM&M wastewater | Bidding | $6m capital. Earth Tech selected preferred bidder 1/2000. |
| Puerto Rico: DBO w/o 7 water plants | Bidding | $300m capital. First project bid 1/2000. |
| Newport, RI : 20-yr. DRO to upgrade 10.7-mgd wastewater plant, correct CSO | Bidding | Cost: NA. RFP: 10/99. |
| Quincy, Wash.: DBO water plant | Bidding | Cost: NA. |
| Seattle, Wash.: 15 to 25-yr. DBO Cedar River 240-mgd water plant | Bidding | $160m capital. Proposals due from three finalists 7/2000. |
| Halifax, N.S., Canada: DBO/F four wastewater plants, pipes | Bidding | $210m capital. RFP to three finalists 2/2000. |
| Phoenix, Ariz.: DBO 80-mgd 1st phase of Lake Pleasant surface water treatment plant and pipeline | Planned | $200m capital. RFQ: 2/2000. |
| Avalon, Calif.: DBO a 1.2-mgd replacement sewage treatment plant | Planned | $13m capital. |
| Sacramento, Calif.: DBO sludge process | Planned | Cost NA. |
| San Diego, Calif: BOT reclaimed water pipeline, effluent marketing | Planned | Cost NA. RFEl 11/99. |
| Fulton County, Ga.: DBO wastewater plant upgrade | Planned | Cost NA. |
| Sioux City, Iowa: 20-yr. DBO 30-mgd wastewater plant, pump, sludge | Planned | $42m capital; $3m O&M. REP 3/2000. |
| City of Lawrence, Mass.: DBO new water plant | Planned | $40m capital. |
| Pawtucket, RI: DBO water system | Planned | $30m to $60m capital. Studies underway. |
| El Paso, Tex.: DBO new 300 to 400-mgd surface water treatment plant | Planned | $500m capital. Studies underway. |
| Houston, Tex.: DBO new Northwest water plant and pipeline | Planned | $175m capital. |
| Vancouver, B.C., Canada: 20-yr. DBO 265-mgd Seymour water treatment plant | Planned | $80m capital. REQ by 5/2000. |