Case Study #4 - Easton Pennsylvania
Compliance Achieved, Consent Decree Removed
The City of Easton, PA, wastewater system serves a population of 55,000 and has peak flows over 20 MGD. A history of problems prior to U.S. Waters management included chronic permit violations, a consent decree, controversies between the city and authority, management labor situations, two supervisors convicted of environmental crimes who were imprisoned, and being on the EPAs blacklist for violations. For the consent order the City paid $389,000 in fines and $120,000 of the plaintiffs legal fees.
The wastewater facility had been managed during this time by a different private contractor but its single manager had no rights of discipline. When Mayor Tom Goldsmith proposed a private company completely take over operation of Eastons water and sewer systems in 1993, not only were some Council members concerned but the union opposed concessions they were asked to make to retain jobs. After a formal Request for Proposals, review of seven proposals, and months of negotiation, council approved U.S. Water L.L.C. as the manager of the two utilities. However, the existing labor agreement covered City workers in many departments not just the water and sewer utilities. After much negotiation and two votes, Local 447 of American Federation of State and Municipal Employees voted to amend its agreement to specifically allow U.S. Water to assume the Citys discipline rights and to work rule efficiency changes. A Council representative was present during all labor negotiations.
U.S. Water replaced the previous manager at the wastewater plant in December 1993 and assumed full operational management responsibilities under this innovative contract for both the wastewater and water systems in May of 1994.
These are the results:
Preceding U.S. Water, the wastewater effluent exceeded its permit limit for phenol in 7 out of 12 months. Since U.S. Waters management, there have been no phenol violations. No capital was required to achieve this.
U.S. Water helped initiate a permit modification in conjunction with the Authority and City. A professional, cooperative relationship with the PA DER and USEPA was established.
Consent decree dropped
$660,000 of savings per year
Improved safety standards
Installed computerized maintenance management system
Revised belt press operations
Changed aerobic digesters into gravity thickeners
Improved anaerobic digester performance
Developed standard operating procedures
Operators are now performing pH testing and routine maintenance tasks
Initiated an electrical curtailment program
Won a citation of merit from the PA DER
Established an improved working relationship with AFSME
Received accolades from the Mayor and Council. This was reported in an Easton Express Times, July 13, 1995 article. See the Mayors comments in Section 8.
Case Study - City of Easton
In the City of Easton, U.S. Water recommendations led to the replacement of polymer feed pumps and belt filter press wash pumps which resulted in increased efficiency in the sludge dewatering operation, including significantly reduced polymer costs. In addition, our recommendations to refurbish the plants engine generator have led to reduced electric expenditures after initiation of an electrical curtailment program at the Easton Wastewater Treatment Plant. Our capital recommendations for the Easton wastewater system have been well received, and have been adopted by the Authoritys Engineer as the basis for continued planning and preliminary design efforts for which receipt of engineering proposals will occur in the near future. U.S. Water personnel will continue to work with the Authority and their engineer throughout the design process, and any construction activities that may follow.
U.S. Water has worked extensively with the City of Easton and its consulting engineers to identify all overflows in the collection system. U.S. Water developed a monitoring and reporting program in response to the regulators concern over dry weather overflows. The sewer maintenance crews under the direction of U.S. Water work to proactively control blockages or clear obstructions that might produce overflows. U.S. Water initiated an overhaul of Eastons pump station generators and pumps to improve efficiency and reliability during storm events. In total these activities have managed to substantially reduce dry weather overflows.U.S. Water has a ten (10) year OM&M contract which includes a 10 MGD wastewater treatment facility. Capital upgrades undertaken at the facility during U.S. Waters tenure have included replacement of primary sludge pumps and major rehabilitation of the primary digester. U.S. Water directed and coordinated all impacted operations to maximize plant performance, expedite construction schedules, and mitigate financial impacts of additional labor costs during construction
In addition, our recommendations to refurbish the plants engine generator have led to reduced electric expenditures after initiation of an electrical curtailment program at the Easton Wastewater Treatment Plant. Our capital recommendations for the Easton wastewater system have been well received, and have been adopted by the Authoritys Engineer as the basis for continued planning and preliminary design efforts for which receipt of engineering proposals will occur in the near future. U.S. Water personnel will continue to work with the Authority and their engineer throughout the design process, and any construction activities that may follow.