|
home
Water Industry News
THE
ISSUES, IMPACT
Issues
- Appleton’s five-year-old $54 million
drinking-water filtration plant is not meeting the
capacity for which it was designed.
- Officials assure that the water is safe and quality
is not in doubt.
- “Ultrafiltration” technology is at the heart of
talks between plant designers and the city.
Impact
- Multimillion dollar changes to the plant are
possible.
- Major water rate hikes have been proposed, including
25 percent
increase for typical households.
- Expensive legal action could be forthcoming.
|
|
Options
for the city
Potential options for dealing with capacity issues at the
Appleton water-filtration plant:
Do nothing. This most likely would limit expansion
of water service for residents and hamper the ability of
|the city to produce water for sale to surrounding
communities in order to save water customers money.
Look for additional technology. This could include
conventional filtration using fine sand or charcoal, to
further treat water before it reaches the existing filter
membranes. This presumably would increase capacity and
prolong the life of membranes.
Enhance existing processes. The city could use
existing processes at the plant, including pre-treatment
methods in place, to increase capacity by adding more
membranes, at a potential cost of more than $5 million. |
|
Water
plant at a glance
Location: Manitowoc Road, City of Menasha
Cost: $54.3 million (budgeted and spent).
Additional costs anticipated.
Design capacity: 24 million gallons a day in warm
weather; 18 million gallons a day in cold weather.
Approved: Common Council, 1998.
Completed and started up: May 2001.
Raw water supply: Lake Winnebago.
Technology: Lime softening; granulated, activated
charcoal; ultrafiltration membrane consisting
of 5.5 million thin, strawlike tubes, each of which are
designed to filter up to five gallons of water a day.
Source: City of Appleton |
|
|
Capacity problems
plague Appleton water plant
Water safe, but
$54M facility not producing supply promised
By
Steve Wideman
Post-Crescent staff writer July
8, 2006
APPLETON — The
city’s water-filtration plant, billed as state-of-the-art when it went
on line five years ago, is failing to produce at promised capacity, and
taxpayers and water customers could face expensive fixes.
The project’s $54
million budget has nearly run dry, The Post-Crescent has learned, and city
leaders are considering spending millions more in improvements, increasing
water rates and taking potentially costly legal action against companies
involved in the project.
Safety of local drinking water is not at issue, officials insist. And
there have been no shortages.
However, the problem is contributing heavily to slumping revenues and
climbing expenses for the city-owned water utility.
Meeting minutes, e-mails and interviews with key people tied to the plant
paint a picture of city leaders prodded by engineers and consultants to
change the plant’s original design and use a new technology despite
warning signs.
One former alderwoman, who voted for the project, said Appleton officials
“failed the community” by not thoroughly scrutinizing the plans, and
now taxpayers and water customers are going to pay the price.
“It’s leadership’s responsibility to ask the right questions,
especially in response to large red flags,” said Jo Egelhoff, who served
on the Common Council from 1993 to 2003.
Mayor Tim Hanna said the city is working diligently to fix the problems as
well as assess financial responsibility for the plant’s failures.
“We are committed to continue optimizing operations to produce what we
paid for at the plant,” he said.
Ald. Jeff Jirschele, head of the Utilities Committee since April, said the
matter is urgent. “We have a challenge to meet that doesn’t leave a
lot of time for casting blame and pointing fingers. We have a multimillion
dollar investment.”
Capacity
questions
The water plant,
south of the city in Menasha, was designed to filter 24 million gallons of
water each day during summer and 18 million gallons a day in winter.
Water is pumped from Lake Winnebago to the plant, where it runs through
various treatment and filter processes, then flows through millions of
pencil lead-thin straws. Those straws, packed into large canisters, are
key to the so-called ultrafiltration or membrane technology.
From early in the operation, however, many of the straws broke.
Through various additional pre-treatment processes and ongoing replacement
of straws, utility operators gradually have brought today’s summer
capacity to near 24 million gallons, according to Utilities Director Mike
Buettner. Last winter, however, capacity was measured at less than 10
million gallons a day, about half of the design, even with extra
pre-treatment.
Although the lower capacity has not created a water shortage for existing
customers, it is preventing the city from selling water to neighboring
communities to help offset costs, said city Finance Director Lisa Maertz.
And the costs for pre-treating the lake water have spilled over the
original budget, meaning any additional dollars will have to come from
taxpayers, be borrowed or be compensated by those responsible for
construction of the plant.
The council recently approved spending $200,000 for consultants to
recommend the best course of action. Among possible answers are
pre-treating water with a sand filter at an unknown cost or adding more of
the controversial straws at a cost of more than $5 million.
For more than a year, the council has met in numerous closed sessions to
discuss possible legal strategies, Hanna said. City officials also have
met with the plant’s designers, technology supplier and project manager,
who have willingly helped address the problems.
The goal is to reach an amicable long-term solution, Hanna said. “The
bottom line is litigation is the avenue of last resort.”
Nicholas Powell, vice president for municipal business at Koch Membrane
Systems, which provided the technology, contends that the plant produced
the promised supply of water during its first couple of years.
“It was not until the end of (2005) that the plant was not able to do
what the contract calls for,” Powell told The P-C recently. “We have
some ideas why and the city has some ideas.”
Powell said his Massachusetts-based company stands ready to help Appleton.
“We are very committed to the city and have never stopped working with
them,” he said. “Eventually, this plant will be just what it is
supposed to be.”
Risky technology?
The ultrafiltration
technology was not included in initial plans for the plant, which aldermen
approved in August 1997 as a two-phase project.
The facility was to help the city meet upcoming deadlines for water
quality standards set by the state Department of Natural Resources. It was
to help produce enough water to meet growth in Appleton as well as
potentially neighboring communities, which would buy from the plant.
The plant would replace a 1914-era facility along the Fox River that had
reached a capacity of 23 million gallons per day.
Plans for the new plant called for using ozone, a form of oxygen used
commercially as an air freshener and water disinfectant, as a final
treatment step.
In early 1998, the city hired McMahon Associates Inc., Neenah, and Carollo
Engineers, Boise, Idaho, for design engineering work, and The Boldt Co.,
Appleton, as construction manager.
The project’s price tag grew from an original estimate of $54.3 million
to $62.7 million after engineers determined more filtering was needed.
Soon after, then-utilities director Duane Leaf, his staff and the
consultants recommended the project be done in a single phase, at the
original lower cost: $54.3 million, and that ultrafiltration be used.
Among the technology’s promised safeguards was blocking of
cryptosporidium, a parasite that slipped through water treatment
facilities in Milwaukee in 1993, killing more than 100 and sickening
400,000.
The tragedy lingered in the minds of Appleton officials, Hanna recalled.
“Absolutely it became a factor (in the decision). How could it not
be?” he said. “Ultrafiltration filters out anything left in the water
after pre-treatment.”
In a report to the council in July 1998, consultants concluded that the
technology was “reliable, mature and cost effective.” A month later,
council members unanimously signed on.
“It was presented as an innovative system and that we would probably be
the first to use it,” Ald. Walter Kalata recalled. “The city spent a
lot of money on studies, the reason being to get the brain work to help us
make the right decision.”
Egelhoff said her vote for approval was based on the less-costly option
and she does not regret it.
“The issue was presented having nothing to do with the ultrafiltration
technology, but rather with the efficiencies of a one-phase versus two-
phase approach,” she said.
Egelhoff said she repeatedly raised concerns in 1998 and 1999, a claim
backed up by meeting minutes and e-mail records.
The city ended up taking too big a risk on unproven technology, she said.
“I pointed out that Koch had no experience with public water plants,
much less with a huge 24 million gallon-a-day plant,” she said. “And
the mayor, Utilities Committee and council were shown ample evidence that
the system absolutely could not operate as promised.”
Powell said the technology was a decade old when Appleton approved it.
And Leaf said much of the plant was designed to use treatment processes
standard to the industry, like traditional clarifiers, charcoal filtering
and lime for softening the water.
“There was nothing prototype or experimental about the plant,” Leaf
said. “Technology is technology and it is always changing. Anything that
involves computers has the possibility of becoming obsolete. That
doesn’t mean the system doesn’t work.”
Trouble surfaces
The first mention of
membrane trouble to the Utilities Committee came in April 2002, according
to meeting minutes.
Leaf told the panel the straws were breaking but that Koch was providing
free replacements. Later meeting records indicate the breaks peaked at
more than 2,000 per month.
In summer 2002, Leaf told the committee the project could have been
completed by early that year but that there was a “significant risk in
that the membranes had not been tested by themselves under a high flow
water condition,” according to the minutes.
“That would have meant whether we accept the project or not there was
still a chance that it would not really work quite the way it was supposed
to.”
Koch stands behind its product, Powell said. The company has dozens of
plants in operation that use technology similar to Appleton’s, but each
plant and water source is unique, he said.
“If you look at water plants that don’t use membranes you’ll find
they have issues, but mostly with water quality and not capacity. Membrane
plants do have issues with water capacity and not water quality.”
Egelhoff said the city should have been open to more bidders. She cites
another membrane supplier, USFilter, then based in Illinois, that raised
concerns early in the project that the plant was being designed
specifically to fit Koch’s membranes.
“Single-source bidding gives carte blanche to one company and is
expensive to taxpayers,” Egelhoff said. “When designers insist on
technology that only one company can provide, that’s always a huge red
flag to decision-makers.”
Hanna said USFilter simply could not provide what the city needed.
“Their filters would not tolerate the use of chlorine, and Appleton uses
chlorine to treat its water.”
Winnebago’s
quirks
One culprit for
Appleton’s water capacity issues is Lake Winnebago, where algae and
sediment are plentiful, Buettner said. Both spell trouble for the membrane
filters.
“Lake Winnebago water really changes and those changes can be very
extreme. … You need to have a facility capable of treating water on the
worst days.” Buettner said.
Leaf, who resigned in 2004 partly due to the plant problems, according to
Hanna, is convinced something other than Mother Nature is at fault.
Koch was chosen to supply the membranes only after tests in which
consultants concluded that the firm’s technology could most effectively
address Winnebago’s water conditions, said Leaf, now a plant
superintendent at the Three Rivers Regional Wastewater Authority in
Longview, Wash.
“That (decreased water flow in winter) was all part of the design. We
knew about the differences between warm and cold water,” Leaf recently
told The P-C. “There is not a scientific reason it shouldn’t be
producing up to 18 million gallons a day in winter. Something is not right
and I’d sure be surprised to find out it was the cold water.”
Hanna said much has changed since Leaf left.
“We are finding out,” Hanna said, “there are scientific reasons (the
plant is not producing to specifications).”
Customer costs
Regardless of the
long-term outcome, Appleton water plant customers — including Grand
Chute and the Waverly Sanitary District — are likely to foot the bill
for added expenses to date.
The draft of a water rates study distributed to aldermen Friday proposes
overall increases of 33 percent, including 25 percent for typical
households. That would amount to about an extra $80 a year, according to
Maertz, the finance director.
She said that since 2002, water utility revenue has dropped by $1.2
million (about 8 percent) while expenses have jumped by $2.8 million (33
percent).
Some of the lost revenue is due to the closure of significant industrial
customers. Maertz attributes $1.8 million or about two-thirds of the added
costs to the increased use of lime, used to soften the water to make it
easier on the membranes, and a change in accounting that charges disposal
of the lime wastewater to the utility.
Maertz said if water capacity could be improved so the city could sell
water to neighboring communities — as originally hoped —
“financially that would help us tremendously.”
The rate increase, which ultimately would need approval from the state
Public Service Commission, would be bad on two fronts, said Mike Spurlock,
an Appleton resident and business owner.
“Residents of Appleton face a double-whammy because businesses will have
to pass on any water cost increases to consumers,” he said.
Grand Chute Town Administrator Mark Rohloff said the town, the city’s
largest customer, would likely contest any rate hike.
“Obviously, this is something we are going to closely scrutinize,”
Rohloff said. “We’ll probably testify before the PSC, because they
(Appleton) are passing problems with their water plant on to the
ratepayers.”
Hanna said the city, like all parties involved in the creation of the
plant, shares in the responsibility. But he hopes finger-pointing as well
as court action can be avoided.
“Litigation is very expensive,” Hanna said. “The outcome is unknown
and it does nothing to improve operations at the plant.”
|